Test without schedule

Need new test, action, option? Post request here.
Post Reply
V Arun
Posts: 52
Joined: Sun Apr 11, 2004 11:17 pm

Test without schedule

Post by V Arun »

Hi Alex,

Is it possible to have tests without any scedule defined ? My requirement is to have a test which will be run by an operator through manual refresh as and when required. The test should be idle at other times (means without any schedule).

I would then group these tests in a folder and would like to just refresh the folder.

Highly appreciate.

Regards,
Arun
KS-Soft
Posts: 13012
Joined: Wed Apr 03, 2002 6:00 pm
Location: USA
Contact:

Post by KS-Soft »

Without schedule at all? No this is impossible. But you may use irregular schedule, so test will be executed once a month. And operator will be able to "refresh" test item at any time (using "Refresh selected test(s)" command).

Regards
Alex
User avatar
plambrecht
Posts: 151
Joined: Wed May 19, 2004 8:11 am
Location: Belgium
Contact:

Post by plambrecht »

Hi,

What about disabling an entire folder ?
When needed, you just enable the folder, and the test are ran immediatly...

btw, in v4.60, when I enable an entire folder, only 1/2 of the items are enabled. When I select the remaining test and enable the selected tests, only 1/2 are enabled...


Pieter

Sorry for the many posts today... I had a productive momemnt :-)
KS-Soft
Posts: 13012
Joined: Wed Apr 03, 2002 6:00 pm
Location: USA
Contact:

Post by KS-Soft »

What about disabling an entire folder ?
When needed, you just enable the folder, and the test are ran immediatly...
Yeah, it should work
btw, in v4.60, when I enable an entire folder, only 1/2 of the items are enabled. When I select the remaining test and enable the selected tests, only 1/2 are enabled...
I cannot reproduce this problem. You have used "Enable this folder" menu item?

Regards
Alex