Posted: Thu May 06, 2010 2:06 am Post subject: Problem with "Synchronize status & alerts" opt |
|
|
Hi.
I have a problem with synchronizing status of dependent tests.
For example i have test named "Test1" with "perform test if" option like "('%::Test2::SimpleStatus%'=='UP') or ('%::Test3::SimpleStatus%'=='UP')" and "Synchronize status & alerts" option enabled. But when "Test2" and "Test3" have status "No answer" "Test1" has "Wait for master" status. I have HM 6.58 installed. As i remember some versions ago with these options "Test1" also had "No answer" status when "Test2" and "Test3" had such status. Is it possible really synchronize dependent test status when all master tests have downed? |
|
Back to top |
|
|
KS-Soft
Joined: 03 Apr 2002 Posts: 12795 Location: USA
|
Posted: Thu May 06, 2010 10:34 am Post subject: |
|
|
Probably you forgot to specify "Otherwise status" parameter?
HostMonitor uses this status for tests that depend on expression...
Regards
Alex |
|