Multiple tests - have one alert

 
Post new topic   Reply to topic    KS-Soft Forum Index -> Configuration, Maintenance, Troubleshooting
View previous topic :: View next topic  
Author Message
mattb



Joined: 28 May 2004
Posts: 8

PostPosted: Fri Jul 09, 2004 4:53 pm    Post subject: Multiple tests - have one alert Reply with quote

We have 44 process tests set up for this one remote machine. What we need to have is an alert that will send out one page/email if any one of those processes goes bad.

I know that we can set up an alert for each one of those tests but if all 44 of them went down at the same time we would get 44 pages/emails. And we don't want that.

All these processes are loosely part of the same app. So if one goes down we just need a page and then one of our admins can log on to the box and see what the problem is.

Please help me know if Host Monitor has this type of functionality.

Thanks
Back to top
View user's profile Send private message
KS-Soft



Joined: 03 Apr 2002
Posts: 12793
Location: USA

PostPosted: Fri Jul 09, 2004 5:50 pm    Post subject: Reply with quote

Probably you can make tests dependant on each other? So, HostMonitor will check main process; if it works, HostMonitor will check another process; and so on....

Regards
Alex
Back to top
View user's profile Send private message Visit poster's website
Mikko



Joined: 21 Jul 2004
Posts: 2

PostPosted: Wed Jul 21, 2004 8:21 am    Post subject: Reply with quote

It's easy to activate only one alert when several tests fail, all you have to do is to make tests dependent of other tests as Alex said. For this to work correctly, each "slave" test must have a slightly higher polling interval than the "master" test, and then you must configure the alerts to execute only if you encounter "No answer" status in the "slave" test two or more times in a row. This is important, because even if the tests are run almost simultaneously, a "slave" (or dependent) test can run just slightly before the "master" test, and then you will get an alert even if you have configured dependencies (if the connection problem appears right after the "master" test, but before the "slave" test).

The problem remains, however, regarding "Good" alert messages, if you have configured tests to send a "Good" alert message once the connection has been restored. If one of the "slave" tests notices the connection problem before the "master" test does it will still change it's status into "No answer", until the "master" test also reacts to the problem and changes it's status to "No answer". Only after that the "slave" test will change it's status to "Waiting for master" (the second time it runs the test). If the "slave" test changes it's status to "No answer" even for a second, it will send a "Good" alert message after the status changes to "Good".

The workaround for this would be a setting where you could force the status of a "slave" test remain as "Host is alive" unless the test result is "No answer" for two or more times and the "master" test status is "Host is alive". Then the status of the "slave" test would not change into "No answer" even for a second before the "master" test has been run at least once after the "slave" test has noticed the problem. In other words, the "master" test would run twice before the "slave" test does, and the "slave" test status would change directly to "Waiting for master", as it should.

I haven't found this kind of setting in HostMonitor, but I hope there will be one in future releases. That would settle this issue for good. If I am mistaken, please do correct me - I would really like to get this thing working!

I'm sorry for this long and confusing explanation, but this is a bit complicated issue.

Regards,

Mikko
Back to top
View user's profile Send private message
KS-Soft



Joined: 03 Apr 2002
Posts: 12793
Location: USA

PostPosted: Wed Jul 21, 2004 9:05 pm    Post subject: Reply with quote

Quote:
The workaround for this would be a setting where you could force the status of a "slave" test remain as "Host is alive" unless the test result is "No answer" for two or more times and the "master" test status is "Host is alive". Then the status of the "slave" test would not change into "No answer" even for a second before the "master" test has been run at least once after the "slave" test has noticed the problem. In other words, the "master" test would run twice before the "slave" test does, and the "slave" test status would change directly to "Waiting for master", as it should.


Some "recheck master test before set Bad/Unknown status for dependant test" option?

Regards
Alex
Back to top
View user's profile Send private message Visit poster's website
Mikko



Joined: 21 Jul 2004
Posts: 2

PostPosted: Thu Jul 22, 2004 3:44 am    Post subject: Reply with quote

Yes, exactly - I'm glad you could figure out what I meant even though I wrote such a long and confusing message...

An option for each test to recheck the status of the master test, or maybe a possibility to define a certain number of "Bad" results before switching the status to "No answer" - that would do it.

Regards,

Mikko
Back to top
View user's profile Send private message
KS-Soft



Joined: 03 Apr 2002
Posts: 12793
Location: USA

PostPosted: Thu Jul 22, 2004 5:12 pm    Post subject: Reply with quote

Quote:
An option for each test to recheck the status of the master test


We have this task in "to do "list

Quote:
or maybe a possibility to define a certain number of "Bad" results before switching the status to "No answer" - that would do it.


What about "Repeat test" action?
http://www.ks-soft.net/hostmon.eng/mframe.htm#actions.htm#actRepeat

Regards
Alex
Back to top
View user's profile Send private message Visit poster's website
MikeeAHM



Joined: 26 Aug 2004
Posts: 5

PostPosted: Thu Aug 26, 2004 3:02 pm    Post subject: Improvement Reply with quote

How about a test method where I check the status of some tests?

I.e. If Ping_Test1 =BAD and Ping_Test2 =GOOD than Message Mike
or if ping_Test1 = BAD and Ping_Test2 = BAD than Message Steven

This would be far more flexible than dependency "kludge" (IMHO)

thanks!

Mike
Back to top
View user's profile Send private message
KS-Soft



Joined: 03 Apr 2002
Posts: 12793
Location: USA

PostPosted: Thu Aug 26, 2004 9:20 pm    Post subject: Reply with quote

You can implement such behavior using "advanced mode" actions
http://www.ks-soft.net/hostmon.eng/mframe.htm#actions.htm#advancedaction

Regards
Alex
Back to top
View user's profile Send private message Visit poster's website
Display posts from previous:   
Post new topic   Reply to topic    KS-Soft Forum Index -> Configuration, Maintenance, Troubleshooting All times are GMT - 6 Hours
Page 1 of 1

 
Jump to:  
You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot vote in polls in this forum


Powered by phpBB © 2001, 2005 phpBB Group

KS-Soft Forum Index