View previous topic :: View next topic |
Author |
Message |
Quantum
Joined: 06 May 2004 Posts: 56
|
Posted: Mon Jul 12, 2004 5:27 am Post subject: My Wishlist |
|
|
1. Remote execution via RMA
2. WMI tests !!!
3. The abillity to have a person acknowlage a bad state
4. Being able to set 0 on the alert repeats
5. User securty to restrict access to test folders in both web and gui.
Just my views, keep up the good work.
Q |
|
Back to top |
|
|
KS-Soft
Joined: 03 Apr 2002 Posts: 12795 Location: USA
|
Posted: Mon Jul 12, 2004 7:04 pm Post subject: |
|
|
We already have items #1, #2, #3, #5 in our "to do" list.
Quote: | 4. Being able to set 0 on the alert repeats |
In other words option to disable the action?
Regards
Alex |
|
Back to top |
|
|
Quantum
Joined: 06 May 2004 Posts: 56
|
Posted: Tue Jul 13, 2004 2:35 am Post subject: |
|
|
He He, I think I messed up on number 4.
I think that I miss under stood the GUI a bit. I read it as do this action and repeat 1 times.
I see that what I means is here is an anction to do 1 times.
option 1 would result in the action being done twice, do the action, then repeat it.
My missunderstanding.
On the others, is there a product roadmap ? do you have release dates ?
Thanks
Q |
|
Back to top |
|
|
KS-Soft
Joined: 03 Apr 2002 Posts: 12795 Location: USA
|
Posted: Tue Jul 13, 2004 12:13 pm Post subject: |
|
|
No, we do not have fixed release dates.
But I think new release will be available within 3 weeks
Regards
Alex |
|
Back to top |
|
|
Quantum
Joined: 06 May 2004 Posts: 56
|
Posted: Mon Aug 02, 2004 5:30 am Post subject: |
|
|
Any news on #1, #2, #3, #5 ? I see we have another version but I can't see any of these in the list.
Thanks
-Q |
|
Back to top |
|
|
KS-Soft
Joined: 03 Apr 2002 Posts: 12795 Location: USA
|
Posted: Mon Aug 02, 2004 1:20 pm Post subject: |
|
|
Come on.. We have done some work http://www.ks-soft.net/hostmon.eng/news.htm Am I right?
And I hope version 4.56 will be available within 2 weeks.
But unfortunately we cannot implement all wishes at once. We have hundreds of tasks in the list.
Approximate implementation order:
1. Remote execution via RMA - probably will be implemented in version 4.70
2. WMI tests - may be version 4.80
3. The abillity to have a person acknowlage a bad state - may be version 4.80 but more likely version 5.0
5. User securty to restrict access to test folders in both web and gui. - - may be version 4.80 but more likely version 5.0
Regards
Alex |
|
Back to top |
|
|
Quantum
Joined: 06 May 2004 Posts: 56
|
Posted: Tue Aug 03, 2004 8:33 am Post subject: |
|
|
Quote: | Approximate implementation order:
1. Remote execution via RMA - probably will be implemented in version 4.70
2. WMI tests - may be version 4.80
3. The abillity to have a person acknowlage a bad state - may be version 4.80 but more likely version 5.0
5. User securty to restrict access to test folders in both web and gui. - - may be version 4.80 but more likely version 5.0
|
That's just what I needed You do tonnes of work and I am sure that we all know that !!
It would be great for the community if there was a roadmap page showing things that you have already taken into the development plan and their version eta (ie not a time just a version).
You would probably find that the posts in here reduce also
Anyhow, thanks for the responce.
-Q |
|
Back to top |
|
|
KS-Soft
Joined: 03 Apr 2002 Posts: 12795 Location: USA
|
Posted: Tue Aug 03, 2004 6:46 pm Post subject: |
|
|
Quote: | It would be great for the community if there was a roadmap page showing things that you have already taken into the development plan and their version eta (ie not a time just a version). |
Problem is - often new requests have higher priority than tasks that already listed. In this case new tasks push some items to the bottom of the list...
Regards
Alex |
|
Back to top |
|
|
|