Posted: Mon Nov 11, 2013 10:15 am Post subject: Deferred nightly actions on test with day-time schedule |
|
|
It seems that when a test is performed between 8 AM and 11 PM, and it has an action profile where one of the actions is performed only between 06 AM and 10 PM with deferred actions, the deferred action will not be performed in the morning if the test goes bad between 10 PM and 11 PM and still is down in the morning when the test schedule starts (at 8 AM).
We were expecting the following:
Day 1:
10.00 PM end of action schedule
10.30 PM test goes bad
11.00 PM end of test schedule
Day 2:
06.00 AM start of action schedule
08.00 AM start of test schedule - deferred action performed
However, the deferred action was nefer performed and the test was bad for 2 days before we discovered the error.
Should this work as expected above, or do we need to make new action profiles matching the schedule of the test, so that the test is always active at the time when the action schedule starts?
Regards,
Patrik |
|
Back to top |
|
|
KS-Soft
Joined: 03 Apr 2002 Posts: 12792 Location: USA
|
Posted: Mon Nov 11, 2013 3:16 pm Post subject: |
|
|
Quote: | It seems that when a test is performed between 8 AM and 11 PM, and it has an action profile where one of the actions is performed only between 06 AM and 10 PM with deferred actions |
That's the reason - actions allowed from 6 AM while test is out of schedule at this time (test probes start from 8 AM).
You may align schedules (just change start time for the actions to 8AM), then it should work in the way you need.
Regards
Alex |
|